(Eagle News)–The Light Rail Transit-1 Cavite extension project is expected to be partially operational by the end of 2021. The Department of Transportation said this was with its right-of-way acquisition almost 100 percent complete, with the remaining obstructions now only consisting of one Maynilad pipe, telco and cable facilities of six companies, and various other ancillary facilities. Only 18 lots have to be acquired, and these are owned by three landowners, DOTr said. According to […]